Dry-dock budgeting: why dockings overrun, and how to control variations

Most docking overruns are decided before the ship enters the dock. How to build the budget, price the unknowns at tender and run variations day by day.

A docking is a project with a hard deadline, a shared budget, a yard that earns more when the scope grows, and a class surveyor at the end who will not sign until the work is done. Superintendents know the feeling of day 9: the hull is blasted, the steel is worse than the gauging said, the propeller polisher is two days late, and the owner wants a number by Friday.

There is no reliable public statistic on how often, or by how much, dockings overrun, and we will not invent one. What experienced superintendents agree on is where overruns come from, and that most of them are decided months before the ship enters the dock. This article sets out the survey rules that fix the timing, how to build a budget that survives the yard, and a variation process that keeps the final invoice close to the plan.

2inspections of the outside of the bottom required in every five-year period (SOLAS regulation I/10).
36 monthsthe longest allowed interval between two bottom inspections.
12 monthshow far ahead a good specification starts.
±3 monthsthe window around each anniversary for annual and intermediate surveys.

The rules that set the date

The docking date is not a commercial choice alone. Under SOLAS Chapter I, regulation 10, a cargo ship needs a minimum of two inspections of the outside of the bottom during any five-year period, and no more than 36 months between any two. Under the harmonized system of survey and certification (HSSC), surveys run on a five-year cycle: annual surveys within three months either side of each anniversary, an intermediate survey around the second or third anniversary, and a renewal survey before the certificate expires.

The five-year survey cycle and the two bottom inspectionsA cargo ship under the harmonized system of survey and certification (HSSC). Source: SOLAS Chapter I, regulation 10; IMO Survey Guidelines under the Harmonized System of Survey and Certification.The five-year survey cycle and the two bottom inspectionsA cargo ship under the harmonized system of survey and certification (HSSC).IssueYear 1Year 2Year 3Year 4Year 5Annual survey windows, 3 months either side of each anniversaryIntermediate survey windowRenewal surveyBottom inspection 1Bottom inspection 2no more than 36 months apartTwo inspections of the outside of the bottom in every five-year period; one normally goes with the renewal survey.Source: SOLAS Chapter I, regulation 10; IMO Survey Guidelines under the Harmonized System of Survey andCertificationWhere the two inspections fall is an example. Flag and class rules on in-water surveys vary.
Figure 1. The five-year survey cycle and the two bottom inspections. Source: SOLAS Chapter I, regulation 10; IMO Survey Guidelines under the Harmonized System of Survey and Certification. Where the two inspections fall is an example.

In practice one docking goes with the renewal (special) survey and one with the intermediate survey. Some ships may replace an intermediate docking with an in-water survey, under flag and class conditions that vary with age and type. Check them early; an in-water survey approved in principle but refused on detail puts a docking back into the plan with no budget.

Two other rules now shape docking scope. The Hong Kong International Convention on ship recycling entered into force on 26 June 2025, and the Inventory of Hazardous Materials must be kept up to date, which matters whenever a docking adds or removes equipment. And the ballast water D-2 standard has applied to all ships since September 2024, so any outstanding treatment work belongs in the next docking plan, not the one after.

Why dockings overrun

How a docking drifts from contract price to final invoiceIllustration, indexed to contract price = 1,000. Dashed: variations a firm specification and survey data could have priced at tender. The axis starts at 800. Source: Naavra, illustration for a synthetic docking; not an industry average, because no reliable public figure exists.How a docking drifts from contract price to final invoiceIllustration, indexed to contract price = 1,000. Dashed: variations a firm specification and survey datacould have priced at tender. The axis starts at 800.8009001,0001,1001,2001,3001,4001,5001,000Contractprice+140Steelgrowth+90Extradock days+60Classfindings+75Owner'sadditions+35Pricevariations1,400FinalinvoiceSource: Naavra, illustration for a synthetic docking; not an industry average, because no reliable publicfigure exists
Figure 2. How a docking drifts from contract price to final invoice. Illustration for a synthetic docking, indexed to contract price = 1,000; not an industry average.

The illustration shows the usual shape of the drift. The largest pieces are the ones a firmer specification could have priced before tender.

How a docking drifts from contract price to final invoice. Illustration for a synthetic docking, indexed to contract price = 1,000; not an industry average.
CauseWhat happensCould it have been priced at tender?
Steel growthGauging was old or thin; blasting reveals more renewalYes: recent gauging, and a unit price per kg for extra steel
Extra dock daysScope grows, or a critical item is latePartly: a daily rate for extra days, and critical path agreed
Class findingsThe surveyor finds items not in the specificationPartly: last survey reports and open conditions in the specification
Owner's additions"While she is in dock" jobs added on the dayYes: a reserve list priced at tender, released by approval
Price variationsUnit rates applied to quantities not in the contractYes: a full schedule of unit rates in the contract
Owner's supply lateSpares, paint or a service engineer arrives lateYes: a delivery plan, tracked weekly from week minus 12

The pattern is clear: overruns mostly come from unknown quantity, not unknown price. The cure is to turn unknown quantities into agreed unit rates before the yard is chosen, and to find as many quantities as possible before the ship arrives.

Build the budget in layers

A docking budget that survives the yard has four layers. Keep them separate in the tender comparison and in the final account, so you can see which layer moved.

LayerWhat is in itHow it is priced
Yard fixedDocking and undocking, dock days, services: electricity, cooling water, fire watch, cranes, garbageLump sums and daily rates from the tender
Specified workHull preparation and painting, valves, sea chests, propeller and shaft work, tanks, machinery jobsQuantity × unit rate, from the specification
Provisional workSteel renewal, extra blasting, extra pipe, extra daysUnit rates agreed at tender; quantity unknown
Owner's costsOwner's supply, class and flag fees, service engineers, superintendent attendance, off-hire, deviation fuelOwner's own quotes and estimates

Then add a contingency that is an explicit number, not a hope. A useful discipline is to set a point, such as 70% of the contingency spent, at which the superintendent goes back to the owner with a revised forecast before any further variation is approved. The figure is an internal control, not an industry norm; choose your own and write it down.

Off-hire is part of the budget

The yard invoice is not the whole cost. Every extra day in dock is a day off hire, and for most ships that is the largest cost of an overrun. Put the ship's daily earnings next to the yard's daily rate in the budget, so a decision to extend by two days is seen at its real price.

The specification, twelve months out

WhenTechnicalCommercial and owner
12 months outCollect survey status, open class items, last docking report, recent gaugingAgree budget envelope and docking window with commercial
9 months outDraft specification by system, with quantities and photosShortlist yards; confirm owner's-supply lead times
6 months outFinal specification; provisional items with unit rates; reserve listTender; compare like for like, layer by layer
3 months outOrder owner's supply; book service engineersContract with full schedule of unit rates and daily rates
Last monthPre-docking meeting; critical path agreed with the yardConfirm off-hire dates with charterers

A specification is only as good as its quantities. "Renew steel as required" is not a specification; it is a blank cheque. "Renew steel as required, estimated 12 tonnes, unit rate per kg agreed" is.

Control variations, day by day

Once the ship is in dock, the specification is fixed and everything else is a variation. Four habits keep variations under control:

  1. One variation log. Every variation gets a number, a description, the reason, the quantity, the unit rate, the total and the approver. Nothing is done without a number.
  2. Approval limits. The superintendent approves up to an agreed amount; above it, the technical manager; above that, the owner. The limits are set before docking, not argued on the day.
  3. Daily progress meeting. The yard's project manager, the superintendent and the chief engineer walk the critical path every morning, and the variation log is read at the same meeting.
  4. Measure before you pay. Steel is weighed or calculated from drawings, blasting area is measured, days are counted from the dock log. Each variation has evidence attached.

Close-out: the account and the record

The docking is not over when the ship floats. The final account should reconcile every line to the specification or a numbered variation, with evidence. The survey status, class reports, updated certificates, the IHM update and the photographs of work done go into the ship's record the same week, while people still remember.

Close-out itemWhy it matters
Final account reconciled to specification and variation logCatches double charges and unapproved work
Class and flag reports filed; certificates updatedThe next Port State officer will ask
Unit rates and quantities recorded per systemThey become the next docking's estimate
Lessons list: what grew, and whyNext time, it goes in the specification

What to do Monday

  • List every ship's next bottom inspection due date against the 36-month limit and the survey windows.
  • For dockings in the next 12 months, check the age of the last gauging; order new gauging where it is old.
  • Put a full schedule of unit rates (steel per kg, blasting per m², pipe per metre, extra days) into every tender.
  • Split each docking budget into yard fixed, specified, provisional and owner's costs.
  • Set approval limits and a contingency review point, in writing, before the ship arrives.
  • Add off-hire per day to every docking budget, next to the yard's daily rate.
  • Start owner's-supply tracking 12 weeks before docking.

Questions and answers

How often must a ship be dry-docked?

Under SOLAS regulation I/10, a cargo ship needs at least two inspections of the outside of the bottom in any five-year period, with no more than 36 months between any two. Some may be in-water surveys, under flag and class conditions.

When does the specification start?

About twelve months before the docking, with survey status, open class items, recent gauging and the last docking report.

Why do dockings overrun?

Mostly from unknown quantities: steel growth after blasting, extra dock days, class findings, owner's additions and late owner's supply. There is no reliable public figure for how often or by how much.

How do you control variations?

One numbered variation log, approval limits set in advance, a daily progress meeting on the critical path, and evidence for every quantity before it is paid.

What should a tender include?

A like-for-like specification with quantities, and a full schedule of unit and daily rates for provisional work, so that growth is priced before the yard is chosen.

What is the real cost of an extra day in dock?

The yard's daily rate plus the ship's lost earnings for that day. For most ships, off-hire is the larger of the two. *This article explains; it is not class or flag guidance. Check your class society's rules and your flag's requirements for your ship.*

Free tool

Ready Score self-check

See the gaps a buyer, a charterer or a Port State officer would see, before they do.

Open the tool

Topics

dry dock cost overrundry docking planningdry dock specification templatedry dock budgetshipyard variation orderspecial survey dockingbottom inspection SOLASdocking close-out

This article explains; it is not legal or regulatory advice. Check the instrument in force for your ship.